Project Scoping Fall/Winter 2017
Public Scoping Meeting November 2017
Develop Purpose and Need Spring 2018
Public Meeting May 2018
Develop Range of Corridor Alternatives Fall/Winter 2018/2019
Public Meeting Spring 2019
Identify Corridor Alternatives Retained for Analysis (CARA) Spring/Summer 2019
Additional Analysis Summer/Fall 2019

Publish Draft Environmental Impact Statement (DEIS) /

Identify MDTA’s Recommended Preferred Corridor Alternative

Winter 2019/2020
Public Hearing Spring 2020
Identify the Preferred Corridor Alternative Summer 2020
Publish Final Environmental Impact Statement (FEIS)/
Record of Decision (ROD)
Winter 2020