Tier 2 Study Overview
The Maryland Transportation Authority (MDTA) and the Federal Highway Administration (FHWA) are following a two-tiered NEPA process for the Bay Crossing Study. The Tier 2 Study will build upon the Tier 1 findings to:
- refine the Purpose and Need to focus on Corridor 7;
- evaluate a No Build alternative and a range of build alternatives including various alignments, crossing types and modal and operational alternatives (e.g. transit, ferries, etc.);
- evaluate traffic, engineering, and environmental impacts;
- provide public involvement and comment opportunities;
- identify a Selected Alternative; and
- identify mitigation measures for unavoidable environmental impacts.
Project Schedule
This schedule is preliminary and subject to change.
April 2022
- Tier 1 Study Completed
(Selected Corridor 7)
June 2022
- Tier 2 Study Funding Secured
- Tier 2 Launched
September 2022
- Initiate Tier 2 Study
- Public and Agency Coordination
- Public Open Houses
October 2023 - December 2025
- Develop Purpose and Need, Traffic, Range of Alternatives, and Environmental Analysis
September 2023
- Public Open Houses
December 2024
- Proposed Alternatives Retained for Detailed Study
- Public Open Houses
2025 Activities
- Engineering and Environmental Analysis of Alternatives Retained for Detailed Study
January 2026
- Draft Environmental Impact Statement Notice of Availability
- MDTA Recommended Preferred Alternative Identified
February 2026
- Draft EIS Public Hearings
Anticipated November 2026
- Tier 2 Study Final Environmental Impact Statement (FEIS) / Record of Decision (ROD)
- Selected Alternative Identified
Anticipated Fall 2026 - Spring 2028
- Procurement for Final Design
Anticipated Spring 2028
- Begin Final Design
Anticipated Summer 2032
- Begin Construction